Approved on Ambition: Five Tests to Run Before the 2027 Change Portfolio Is Committed

Jenesys Associates
Approved on Ambition: Five Tests to Run Before the 2027 Change Portfolio Is Committed

Photo: Governor Glenn Youngkin, CC BY 2.0, via Wikimedia Commons

By late November, most UK organisations have a 2027 change portfolio in draft. It has been shaped by strategy days, filtered through finance and dressed for the board in a familiar format: objective, cost, benefit, timeline. What it rarely contains is any evidence that the operation on which it depends can absorb it.

The gap matters because approval is a commitment of reputation as much as capital. A portfolio signed off in December becomes, by February, a set of promises being defended rather than examined. The pre-commitment audit is a short, deliberately unglamorous exercise designed to sit in the weeks between draft and sign-off, while there is still room to remove, sequence or reshape the work.

A business case tests value; this tests capacity

A conventional business case answers one question: is this worth doing? It does not answer the question that determines the year — can we do it, alongside everything else, without damaging the service we are already running? Those are different judgements, taken by different people, and only the first tends to be documented.

The pre-commitment audit is not a challenge to strategy. It is a check that the portfolio is affordable in the currency that actually constrains delivery: managerial attention, specialist time and operational headroom.

Test one: named ownership, at the right level

Every initiative should have one named individual accountable for it. Not a function, not a steering group, not a sponsor whose involvement is ceremonial. A person whose name appears, who has the authority to stop the work, and who has a credible amount of time allocated to the role.

A useful question to put to each owner: if this had failed by September, whose diary would be cleared to deal with it? If the honest answer is a committee, the initiative fails the test. Shared accountability at the top is one of the more reliable predictors of drift.

Test two: capacity borrowing, declared and agreed

Every change borrows from business as usual. It borrows subject-matter experts, team managers' attention, cover arrangements and the goodwill of the people asked to test, train and absorb something new. The borrowing is real even when it is not recorded.

Ask each initiative to state, in plain terms, what it takes from operations between January and June — in hours or full-time equivalents by month — and who in the operation has agreed to that loan. Where a programme cannot produce the number, treat it as unquantified rather than negligible. Several unquantified programmes in the same department is how a quiet capacity crisis is assembled.

Test three: stop conditions, written in advance

A stop condition is the evidence that would cause the organisation to pause, reshape or close an initiative. It is written before the work begins, when the people involved are still capable of being dispassionate.

Good stop conditions are specific and observable: adoption below an agreed threshold at day thirty; cost to serve unchanged by month four; a critical dependency not delivered by a stated date; a regulator or customer obligation that has shifted. The test is not whether a document mentions risk. It is whether a dated, invocable condition exists and someone is empowered to act on it.

Test four: the post-go-live review has a date and an owner

Go-live is the beginning of the evidence, not the end of the project. A post-implementation review that exists only as an intention will not happen, because by the time it is due the people who would run it have moved to the next thing.

At pre-commitment stage, each initiative should be able to show a review date in the calendar, a named owner and a defined set of measures. Where those three are absent, the benefit case is effectively untestable.

Test five: a baseline taken before anything changes

Benefits are asserted far more often than they are measured. The remedy is unglamorous: capture the current state first. Cost per transaction, cycle time, error or rework rate, complaint volume, customer effort — whatever the initiative claims to improve should be measured in the month before mobilisation.

Without a baseline, the organisation cannot tell improvement from redistribution, and the post-go-live review becomes a discussion about perception.

Running the audit inside the planning cycle

The exercise can be completed in a fortnight. One facilitator, a template of five questions per initiative, a forty-minute conversation with each owner, and a single triage session at the end. Initiatives come out in one of three states: commit, condition or defer.

Conditional approval is where the value lies, provided the condition is specific and has a date by which it must be met. A condition without a deadline is a deferral with better presentation.

What to do with the findings

Expect a fifth of the portfolio to move to the following year and a third to carry conditions. Present the results to the board as capacity data rather than as criticism: this is what the organisation can absorb, this is what it would cost to absorb more, and this is the sequence that keeps the service intact.

There is a political dimension. Deferral feels like loss to the person who sponsored the work, and the conversation is easier if the audit is agreed before the portfolio is formed rather than after. Framing it as sequencing rather than rejection helps; so does being explicit that a portfolio of eight deliverable changes outperforms fifteen that all slip.

The question to settle before December

The test of a 2027 portfolio is not whether it is ambitious. It is whether it is honest about what it will take from the operation, and whether anyone has written down, in advance, what would cause the organisation to stop. Settling both before sign-off is considerably cheaper than settling them in September.

All Articles

Related Articles

Notice to Quit: Auditing a Service Before You Switch It Off

Notice to Quit: Auditing a Service Before You Switch It Off

The Corridor Verdict: Auditing Decisions That Never Reach the Record

The Corridor Verdict: Auditing Decisions That Never Reach the Record

Performance on Credit: Auditing the Reviews Your Change Programme Deferred

Performance on Credit: Auditing the Reviews Your Change Programme Deferred